OFFSHORE WIND๐Ÿ”ฅ HIGH

OranjeWind Offshore Wind Farm

๐Ÿ‡ณ๐Ÿ‡ฑ Netherlands ยท 795 MW (53 x Vestas V236-15.0 MW turbines)

DEVELOPER / CLIENT

RWE (50%), TotalEnergies (50%)

PHASE

Installation

EXPECTED COMPLETION

2028 (full commissioning)

LAST UPDATED

2026.09.02

What's Happening

On September 1, 2026, Jan De Nul's heavy-lift vessel Les Alizes installed the first of 53 monopile foundations, 53 km off the Dutch coast in the Hollandse Kust West zone. Each monopile is roughly 90 meters long and 8 meters in diameter, supplied by Sif and transported from its Maasvlakte II facility near Rotterdam. Bubble curtain technology is being used during piling to limit underwater noise. The foundation campaign is expected to run through early 2027.

NEXT MILESTONE โ€” Inter-array cable installation (114 km total, via DEME) starts late 2026, followed by turbine installation throughout 2027 using Jan De Nul's jack-up vessel Voltaire.

SOURCE โ†—

Project Timeline

  1. Developmentโ†’
  2. Permittingโ†’
  3. FEEDโ†’
  4. Tenderโ†’
  5. Contract Awardedโ†’
  6. Detailed Engineeringโ†’
  7. Fabricationโ†’
  8. Constructionโ†’
  9. Installationโ†’
  10. Commissioningโ†’
  11. Operational

Path to Construction

The concrete steps still ahead for this specific project โ€” not just its current phase label.

  1. 01Complete monopile foundation installation across all 53 positions (expected by early 2027).
  2. 02Install 114 km of inter-array cabling connecting turbines to the offshore substation, starting late 2026.
  3. 03Install all 53 Vestas V236-15.0 MW turbines using the Voltaire jack-up vessel, throughout 2027.
  4. 04Complete the offshore AC grid connection via TenneT's Hollandse Kust West Beta platform.
  5. 05Commission and energize the full 795 MW wind farm, targeted for 2028.

Companies Involved

DEVELOPER / CLIENT

  • TotalEnergies
  • RWE

FABRICATOR

  • Sif

OEM

  • Vestas

OTHER

  • TenneT

MARINE CONTRACTOR

  • Jan De Nul
  • DEME

Hiring Outlook

๐Ÿ”ฅ HIGH

Active offshore foundation installation just began, with Jan De Nul and DEME both mobilized and cable/turbine installation following through 2027 โ€” sustained marine construction demand for roughly two years before commissioning.

LIKELY DISCIPLINES

Marine installationFoundation engineeringHSEMarine coordinationCommissioning

This is an MW Daily outlook based on project phase and activity โ€” not confirmed vacancy information.

Follow This Project

We'll email you when OranjeWind Offshore Wind Farm has a real update โ€” new contract, phase change, or a related job.