OranjeWind Offshore Wind Farm
๐ณ๐ฑ Netherlands ยท 795 MW (53 x Vestas V236-15.0 MW turbines)
DEVELOPER / CLIENT
RWE (50%), TotalEnergies (50%)
PHASE
Installation
EXPECTED COMPLETION
2028 (full commissioning)
LAST UPDATED
2026.09.02
What's Happening
On September 1, 2026, Jan De Nul's heavy-lift vessel Les Alizes installed the first of 53 monopile foundations, 53 km off the Dutch coast in the Hollandse Kust West zone. Each monopile is roughly 90 meters long and 8 meters in diameter, supplied by Sif and transported from its Maasvlakte II facility near Rotterdam. Bubble curtain technology is being used during piling to limit underwater noise. The foundation campaign is expected to run through early 2027.
NEXT MILESTONE โ Inter-array cable installation (114 km total, via DEME) starts late 2026, followed by turbine installation throughout 2027 using Jan De Nul's jack-up vessel Voltaire.
Project Timeline
- Developmentโ
- Permittingโ
- FEEDโ
- Tenderโ
- Contract Awardedโ
- Detailed Engineeringโ
- Fabricationโ
- Constructionโ
- Installationโ
- Commissioningโ
- Operational
Path to Construction
The concrete steps still ahead for this specific project โ not just its current phase label.
- 01Complete monopile foundation installation across all 53 positions (expected by early 2027).
- 02Install 114 km of inter-array cabling connecting turbines to the offshore substation, starting late 2026.
- 03Install all 53 Vestas V236-15.0 MW turbines using the Voltaire jack-up vessel, throughout 2027.
- 04Complete the offshore AC grid connection via TenneT's Hollandse Kust West Beta platform.
- 05Commission and energize the full 795 MW wind farm, targeted for 2028.
Companies Involved
DEVELOPER / CLIENT
- TotalEnergies
- RWE
FABRICATOR
- Sif
OEM
- Vestas
OTHER
- TenneT
MARINE CONTRACTOR
- Jan De Nul
- DEME
Hiring Outlook
๐ฅ HIGHActive offshore foundation installation just began, with Jan De Nul and DEME both mobilized and cable/turbine installation following through 2027 โ sustained marine construction demand for roughly two years before commissioning.
LIKELY DISCIPLINES
This is an MW Daily outlook based on project phase and activity โ not confirmed vacancy information.
Follow This Project
We'll email you when OranjeWind Offshore Wind Farm has a real update โ new contract, phase change, or a related job.