Dogger Bank Wind Farm
π¬π§ United Kingdom Β· 3.6 GW (phases A, B, C combined)
DEVELOPER / CLIENT
SSE Renewables (40%), Equinor (40%), VΓ₯rgrΓΈnn (20%)
PHASE
Installation
EXPECTED COMPLETION
2027 (phases B/C)
LAST UPDATED
2026.08.30
What's Happening
As of July 2026, all wind turbine generators and inter-array cables are installed on Dogger Bank A. Seaway7 is transporting and installing foundations across all three phases, with the Seaway Ventus jack-up vessel beginning GE Vernova Haliade-X turbine installation work in mid-2026. Heerema Marine Contractors is handling Dogger Bank C foundations, and Saipem is transporting and installing the offshore substation platforms for phases A and B.
NEXT MILESTONE β Continued turbine and foundation installation across Dogger Bank B and C through 2026.
Project Timeline
- Developmentβ
- Permittingβ
- FEEDβ
- Tenderβ
- Contract Awardedβ
- Detailed Engineeringβ
- Fabricationβ
- Constructionβ
- Installationβ
- Commissioningβ
- Operational
Path to Construction
The concrete steps still ahead for this specific project β not just its current phase label.
- 01Complete remaining foundation installation on Dogger Bank B and C (Seaway7 and Heerema Marine Contractors, respectively).
- 02Complete offshore substation platform installation on remaining phases (Saipem).
- 03Complete turbine installation on Phases B and C using the Seaway Ventus jack-up vessel β GE Vernova Haliade-X turbines, work beginning mid-2026.
- 04Finish inter-array and export cable installation for the remaining phases.
- 05Commission each phase individually as it completes construction β Phase A is furthest along.
- 06Full commercial operation across all three phases, targeted for 2027.
Companies Involved
DEVELOPER / CLIENT
- SSE Renewables
- Equinor
- VΓ₯rgrΓΈnn
INSTALLATION CONTRACTOR
- Seaway7
- Saipem
- Heerema Marine Contractors
OEM
- GE Vernova
Hiring Outlook
π₯ HIGHActive, concurrent installation work across three project phases with multiple named marine contractors already mobilized β this is peak offshore construction activity.
LIKELY DISCIPLINES
This is an MW Daily outlook based on project phase and activity β not confirmed vacancy information.