What's Happening

As of July 2026, all wind turbine generators and inter-array cables are installed on Dogger Bank A. Seaway7 is transporting and installing foundations across all three phases, with the Seaway Ventus jack-up vessel beginning GE Vernova Haliade-X turbine installation work in mid-2026. Heerema Marine Contractors is handling Dogger Bank C foundations, and Saipem is transporting and installing the offshore substation platforms for phases A and B.

NEXT MILESTONE β€” Continued turbine and foundation installation across Dogger Bank B and C through 2026.

SOURCE β†—

Project Timeline

  1. Development→
  2. Permitting→
  3. FEED→
  4. Tender→
  5. Contract Awarded→
  6. Detailed Engineering→
  7. Fabrication→
  8. Construction→
  9. Installation→
  10. Commissioning→
  11. Operational

Path to Construction

The concrete steps still ahead for this specific project β€” not just its current phase label.

  1. 01Complete remaining foundation installation on Dogger Bank B and C (Seaway7 and Heerema Marine Contractors, respectively).
  2. 02Complete offshore substation platform installation on remaining phases (Saipem).
  3. 03Complete turbine installation on Phases B and C using the Seaway Ventus jack-up vessel β€” GE Vernova Haliade-X turbines, work beginning mid-2026.
  4. 04Finish inter-array and export cable installation for the remaining phases.
  5. 05Commission each phase individually as it completes construction β€” Phase A is furthest along.
  6. 06Full commercial operation across all three phases, targeted for 2027.

Companies Involved

DEVELOPER / CLIENT

  • SSE Renewables
  • Equinor
  • VΓ₯rgrΓΈnn

INSTALLATION CONTRACTOR

  • Seaway7
  • Saipem
  • Heerema Marine Contractors

OEM

  • GE Vernova

Hiring Outlook

πŸ”₯ HIGH

Active, concurrent installation work across three project phases with multiple named marine contractors already mobilized β€” this is peak offshore construction activity.

LIKELY DISCIPLINES

Marine installationCommissioningHSEMechanical completionSite supervision

This is an MW Daily outlook based on project phase and activity β€” not confirmed vacancy information.

Follow This Project

We'll email you when Dogger Bank Wind Farm has a real update β€” new contract, phase change, or a related job.